Circula Panorama Pipeline Replacement Project
2.28.24 Project Map_Circula Panorama.png
Construction Schedule:

East Orange County Water District (EOCWD) will soon be conducting ongoing construction activities in your neighborhood as part of the Circula Panorama Pipeline Project. Please plan ahead, leave early, and allow extra time to reach your destination. 


Construction is anticipated to begin in April 2024 along Circula Panorama and ancillary streets. Construction in the area will last approximately six months until completion. 


Construction hours are 7:00 a.m. to 5:00 p.m. Monday through Friday and some Saturdays. Please keep in mind that inclement weather may necessitate schedule changes.

What to Expect During Construction:
  • Street lanes may be restricted. Pedestrian access will be available.

  • Occassional water service interruptions.

  • Increased truck and construction traffic.

  • Noise, dust and vibrations.

  • Signs will be posted if any temporary parking restrictions are necessary.

Project Benefits:
  • Replaces 3,200 feet of aging pipe.

  • Upsizes pipe from 6" to 12" pipe.

  • Installs three (3) pressure reducing stations.

  • Improves water supply reliability.

Why is the Project Needed?
  • Replaces 40-70 year old pipes.

  • Provides secondary supply pipeline to Panorama Heights.

  • Improves both water flow and pressure for homes near the project area.

How to Stay Informed:
  • Contact Operations Manager, Jerry Mendzer at 714-538-5815

bottom of page