
CONSTRUCTION SCHEDULE ALERT NOTICE
.png)
BROWNING STREET DETOUR
Beginning February 2, and lasting approximately two weeks, northbound lanes on Browning Ave. between El Camino Real and Parkview Way will be closed. This closure will allow a better flow of traffic in and out of the school parking lot and minimized impact to the residential neighborhoods. Please follow all signage, expect construction delays and plan accordingly to give yourself enough time to get to your destination.

Project Overview
The East Orange County Water District plans to upgrade and enhance the reliability of sewer systems serving Tustin and North Tustin residents and in other areas being served. The system dates back to 1962 and some aging sewer lines are in need of repairs/replacements to ensure toilets, shower and sink drains remain operational. Select sewer lines are also going to be upsized, allowing for continued reliability with future population growth.
Following an extensive study, East Orange County Water District identified the following areas of the sewer system needing improvement: Browning Avenue, Fallen Leaf, 6th Street, Clarissa Lane and Crawford Canyon.
At-a-Glance Info
AFFECTED CITIES:
Tustin, Unincorporated Orange County
PROJECT COST:
$16 million
ESTIMATED TIMELINE:
Environmental Permitting/Design Phase:
Spring 2020 - Summer 2021
Construction Phase:
Summer 2021 - Summer 2022
View the Initial Study environmental report for the EOCWD Sewer Reliability: Capacity Rehabilitation & Augmentation Project by clicking on the PDF icon to the left or the link below.
Thank you for your time and interest in this important public utilities improvement project!
Environmental Permitting Phase
-
Project impacts are identified, such as traffic and noise.
-
Project alternatives and options presented. Construction methods discussed.
-
Public input and comment are received.
-
Project goes before EOCWD Board of Directors for adoption, at a Public Hearing in which members of the public may comment.
Design Phase
-
Selected alternative receives final design.
-
Construction schedule is developed.
-
Construction contractor selected.
Construction Phase
-
Project undergoes construction.
-
Project is commissioned for use.

There are 5 project segments:
Browning Avenue, Fallen Leaf, 6th Street, Clarissa Lane and Crawford Canyon

Browning Avenue Segment
Project Benefits
-
Installs a redundant 300 foot sewer pipe crossing under the 5 fwy
-
Replaces more than 3,700 feet of aging sewer pipe constructed in 1962
-
Upsizes sewer pipe from 10- and 12-inch pipes to 15- and 18-inch pipes
-
Existing sewer lines remain in service during construction

Fallen Leaf Segment
Project Benefits
-
Installs approximately 300 feet of new sewer pipe, replacing aging sewer pipe constructed in 1962
-
Installs 21-inch sewer pipes, allowing for continued reliability and expected capacity needs
-
Existing sewer lines remain in service during construction

6th Street Segment
Project Benefits
-
Installs new 10-inch sewer pipe, allowing for continued reliability and expected capacity needs

Clarissa Lane Segment
Project Benefits
-
Replaces a 500 feet of aging sewer pipe constructed in 1962
-
Upsizes sewer pipe from 6-inch to 8-inch pipes, allowing for continued reliability and expected capacity needs
-
Existing sewer lines remain in service during construction

Crawford Canyon Segment
Project Benefits
-
Replaces 600 feet of aging sewer pipe
-
Upsizes sewer pipe from 8-inch to 12-inch pipes, allowing for continued reliability and expected capacity needs
-
Existing sewer lines remain in service during construction


Construction Methods
Open Trench Excavation
Workers dig down to expose the existing pipe. Then the pipe is removed and replaced, and the trench is backfilled.
Jack and Bore
Crews dig pits at both ends of a pipeline to be replaced. A special machine creates a tunnel without disturbing the surface, allowing the old pipe to be removed and a new one pushed into place.

Pipe Example
-
Replacement sewer pipes will be upsized for continued reliability and future growth.
-
Sizes range from 8 inches to 21 inches in diameter.
